Trump Endeavor 12, LLC v. Fernich, Inc. d/b/a The Paint Spot, Opinion
Reporting cited here
- documented
During 2014, Trump Endeavor obtained paint materials for the Doral project under a payment obligation to The Paint Spot.
Factual background, 2014 supply transactions and payment obligationThe Paint Spot Judgment — Promised · Promised
- documented
After nonpayment, The Paint Spot recorded a construction lien for $32,535.87.
Lien date and amount in factual backgroundThe Paint Spot Judgment — The record · The record
- documented
After nonpayment, The Paint Spot recorded a construction lien for $32,535.87.
Factual background, 2014 supply transactions and payment obligationThe Paint Spot Judgment — The record · The record
- documented
The adjudicated debtor was the Trump entity that owned the Doral property.
Factual background, 2014 supply transactions and payment obligationThe Paint Spot Judgment — The record · The record
- documented
The Paint Spot matter is an adjudicated example of a small supplier forced to use a lien and litigation to collect, but it cannot validate every other contractor claim.
Factual background, 2014 supply transactions and payment obligationThe Paint Spot Judgment — Audit finding · Cited analysis
- documented
The Paint Spot matter is an adjudicated example of a small supplier forced to use a lien and litigation to collect, but it cannot validate every other contractor claim.
Lien date and amount in factual backgroundThe Paint Spot Judgment — Audit finding · Cited analysis
- documented
The Paint Spot matter is an adjudicated example of a small supplier forced to use a lien and litigation to collect, but it cannot validate every other contractor claim.
Holding and conclusionThe Paint Spot Judgment — Audit finding · Cited analysis
- documented
The appellate court affirmed liability and entitlement to attorney fees after the supplier prevailed below.
Holding and conclusionThe Paint Spot Judgment — Outcome · Outcome