Southwest Border: Additional Actions Needed to Address Cultural and Natural Resource Impacts from Barrier Construction
Reporting cited here
- documented
GAO found that CBP and the Department of Defense installed about 458 miles of border-barrier panels from January 2017 through January 2021 and that 81 percent of those miles replaced existing barriers. GAO also reported cultural and natural-resource harms, including effects on tribal burial sites, water sources, endangered species and erosion.
What GAO Found and Fast FactsTrump border-barrier program drew on DHS appropriations, redirected defense funds and a Treasury transfer · Historical funding authority, transfers and construction outputs; no combined spending total